Estimated Completion Dates:

Design - 100% construction documents: January 2025

Pre-solicitation for Construction release: March 13, 2025
BIBE 317515 Replace Chisos Lodge Rehab Water

Solicitation for Construction released: April 2025

Construction contract awarded: June 2025

Full Notice to Proceed: July 2025

Construction Completion: July 2027

 
Visitors at the Chisos Basin Store

Chisos Basin Visitor Services
schedule for operations

Current as of March, 20

Chisos Basin Campground & Group Campground
Open through June 29, 2025

Chisos Basin Visitor Center
Open through June 30, 2025

Chisos Basin Camper Store
Open through June 12, 2025

Chisos Mountains Restaurant
Open through June 12, 2025

Chisos Mountains Lodge
Open through the night of June 11, 2025
During the temporary closure of Chisos Mountains Lodge, we invite park visitors to stay and experience the newly remodeled Big Bend Station near the park entrance and the town of Terlingua.
 
 
 
Sunrise scene at Panther Junction

Big Bend National Park remains open throughout this project. Only the Chisos Basin area of the park will be affected. Over 800,000 acres and hundreds of miles of scenic drives (paved/unpaved), developed and primitive campsites, river access, and over 150 miles of hiking trails will remain open for visitors from around the world to enjoy.

Image credit: NPS

Last updated: March 20, 2025

Park footer

Contact Info

Mailing Address:

PO Box 129
Big Bend National Park, TX 79834-0129

Phone:

432-477-2251

Contact Us